Phase 5: Testing and validation
Considering migration scope of 1 cluster | 100+ applications. The following represent the testing and validation effort.
Activity | Effort (Hours) |
|---|---|
Functional testing | 120 |
Integration testing | 80 |
Performance and load testing | 60 |
Security scanning and validation | 48 |
Disaster recovery testing | 40 |
UAT coordination and support | 60 |
Defect resolution | 80 |
Sign-off documentation | 16 |